Dear Mr Ghods,

Thank you very much for your kind wishes - same to you and your family.
For the suggested additional assistance in the area of technical support, please consider the following:
1) There is a need to elaborate on the main focus and issues of interest to be covered for each of tasks.
2) In some of the areas there was already assistance during 2012-2013, e.g.:
* task 1.2.1 on "Routine core analysis for safe operation" EM postponed from Nov. 2013 to 27-30 April 2014. How it is linked to the new WS on "Core management calculation during NPP operation"?
*Task 1.3.1 completed already WS in November 2013 on "Practical application of Living PSA for safe operation" and summary report with recommendations provided. Is the new WS on "Leaving PSA for the NPP operation a follow-up on some of recommendations? Please specify.
* How the newly requested WS on "Core management calculation during NPP operation" is linked to the planned tasks 1.22.1 and 1.23.1 for which a condition for implementation is availability of relevant computer codes?
* As for the newly requested WS on "V&V of thermal hydraulic model for the accident analysis of BNPP" is the model available in order to proceed with its V&V?
Please advise.

Best regards,
B. Gueorguiev

-----Original Message-----
From: ghods@nppd.co.ir [mailto:ghods@nppd.co.ir]
Sent: Sunday, 22 December 2013 14:48
To: GUEORGUIEV, Boris
Cc: rahnama; mghods2004
Subject: suggestion of new tasks for TSO

Dear Mr. B. Gueorguiev
I would like to take this opportunity for greeting New Year wishing all the best for You and Your Family in coming year.
Please be informed that have studied the TC of the technical cooperation with IAEA, considering the tasks and duties of technical support company it is suggested that following tasks could be included in TC programme:
1- Workshop on “Core management calculation during NPP operation”.
2- Workshop on “Fuel integrity monitoring during NPP operation”.
3- Workshop on “Spend fuel monitoring during NPP operation”.
4- Workshop on “Living PSA for the BNPP”.
5- Workshop on “V&V of thermal hydraulic model for the accident analysis of BNPP”.
You are kindly requested to inform me on Your opinion about a.m. suggestion.
Adding that according to coordination with Mr. Rahnama, the issue will be discussed during Your next trip to IRAN.

Best Regards.
M.Ghods

This email message is intended only for the use of the named recipient. Information contained in this email message and its attachments may be privileged, confidential and protected from disclosure. If you are not the intended recipient, please do not read, copy, use or disclose this communication to others. Also please notify the sender by replying to this message and then delete it from your system.